Project #21928 - Integrated cost/schedule control

Following are cost and schedule data for a project that is underway.

 

 

 Month

1

2

3

4

5

6

7

8

9

10

11

12

Planned

30

35

42

46

40

52

45

48

50

40

30

15

Actual

10

25

47

55

52

54

50

58

PROJECT COST DATA

 

 

Task

Planned start

Planned Duration

Actual start

Actual Duration

A

Beginning Month 1

2 months

Beginning Month 2

2.5 months

B

Beginning Month 2

3 months

Beginning Month 3

4 months

C

Beginning Month 4

3 months

Beginning Month 5

3.5 months

D

Beginning Month 6

5 months

Beginning Month 7

2 months so far

E

Beginning Month 8

4 months

Not yet begun

F

Beginning Month 10

3 months

Not yet begun

PROJECT SCHEDULE DATA

 

1. Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs

2. Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance

 

3. Summarize in words what you see project status to be at this time. What do you predict regarding the final cost and final schedule for the project?

Subject Business
Due By (Pacific Time) 02/16/2014 12:00 am
Report DMCA
TutorRating
pallavi

Chat Now!

out of 1971 reviews
More..
amosmm

Chat Now!

out of 766 reviews
More..
PhyzKyd

Chat Now!

out of 1164 reviews
More..
rajdeep77

Chat Now!

out of 721 reviews
More..
sctys

Chat Now!

out of 1600 reviews
More..
sharadgreen

Chat Now!

out of 770 reviews
More..
topnotcher

Chat Now!

out of 766 reviews
More..
XXXIAO

Chat Now!

out of 680 reviews
More..
All Rights Reserved. Copyright by AceMyHW.com - Copyright Policy