Project #53356 - Using PERT in Scheduling Projects

PERT is a scheduling system that is widely used in businesses to help organize and control the completion of a major project.  Table 1 lists the tasks, the time required to complete the tasks of the assembly of a particular product in the SmartView company, and the dependency among these tasks. 

 

Table 1

Task

Time Required (Days)

Preceding Tasks

1. A

5

None

2. B

7

None

3. C

4

A

4. D

5

A, B, C, E

5. E

6

B

6. F

7

A, B, C, D, E

7. G

4

A, B, C, D, E

8. H

3

A, B, C, D, E, F, G

Using table 1:

  1. Choose the graph that is the closest to the table.

  2. In your selected chart, list all possible paths and determine the total completion time of each path.
  3. In your selected chart, determine the critical path and the earliest time needed to complete all tasks on the critical path.
  4. In your selected chart, determine a critical path for task D.

Subject Mathematics
Due By (Pacific Time) 01/12/2015 12:00 pm
Report DMCA
TutorRating
pallavi

Chat Now!

out of 1971 reviews
More..
amosmm

Chat Now!

out of 766 reviews
More..
PhyzKyd

Chat Now!

out of 1164 reviews
More..
rajdeep77

Chat Now!

out of 721 reviews
More..
sctys

Chat Now!

out of 1600 reviews
More..
sharadgreen

Chat Now!

out of 770 reviews
More..
topnotcher

Chat Now!

out of 766 reviews
More..
XXXIAO

Chat Now!

out of 680 reviews
More..
All Rights Reserved. Copyright by AceMyHW.com - Copyright Policy