Project #66038 - Earn Value Analysis

Earn Value Analysis

Estimated total cost = $ 16.5 x 10000

Estimated project duration = 8 weeks

Using the Earned Value analysis (EVA), the project progress status for the first 4 weeks is given the table below: (x10000)

 

 

Week

1

2

3

4

5

6

7

8

BCWS, 10000

1

3

5

8

11

13.5

15.5

16.5

BCWP, 10000

1.3

3

3.3

13.44

-

-

-

-

ACWP, 10000

1.4

2.4

5.5

9.6

-

-

-

-

 

1) Apply the Schedule Performance Index (SPI) and Cost Performance Index (CPI) to indicate the project status for the first 4 weeks.

2) Draw the SPI vs. CPI diagram for the project progress through weeks 1 to 4.

3) Based on week 4 status, Estimate Cost at Completion (ECAC) for this project.

Subject General
Due By (Pacific Time) 04/10/2015 03:40 pm
Report DMCA
TutorRating
pallavi

Chat Now!

out of 1971 reviews
More..
amosmm

Chat Now!

out of 766 reviews
More..
PhyzKyd

Chat Now!

out of 1164 reviews
More..
rajdeep77

Chat Now!

out of 721 reviews
More..
sctys

Chat Now!

out of 1600 reviews
More..
sharadgreen

Chat Now!

out of 770 reviews
More..
topnotcher

Chat Now!

out of 766 reviews
More..
XXXIAO

Chat Now!

out of 680 reviews
More..
All Rights Reserved. Copyright by AceMyHW.com - Copyright Policy