Project #68415 - Operations Managment

 

Assume that you are the manager of a shop that assembles power tools. You have just received an order for 53 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is

 


 

 

Item

Lead Time (weeks)

On Hand

    Components

Saw

2

15      

  A(2), B(1), C(4)

A

1

10      

  E(3), D(1)

B

2

5      

  D(2), F(3)

C

2

65      

  E(2), D(2)

D

1

20      

 

E

1

10      

 

F

2

30      

 


 


 

 

b.

Develop the material requirements plan for component E using lot-for-lot ordering. (Leave no cells blank - be certain to enter "0" wherever required.)

 


 

 

  Item: E(3) & E(2) LT = 1 wk.

      Beg. Inv.

       1

     2

     3

     4

     5

    6

    7

    8

  Gross requirements

               

 

  Scheduled receipts

 

 

 

 

 

 

 

 

  

  Projected on hand

               

 

  Net requirements

               

 

  Planned order receipt

               

 

  Planned order release

               

 

 

 

 

Subject Business
Due By (Pacific Time) 04/26/2015 01:00 pm
Report DMCA
TutorRating
pallavi

Chat Now!

out of 1971 reviews
More..
amosmm

Chat Now!

out of 766 reviews
More..
PhyzKyd

Chat Now!

out of 1164 reviews
More..
rajdeep77

Chat Now!

out of 721 reviews
More..
sctys

Chat Now!

out of 1600 reviews
More..
sharadgreen

Chat Now!

out of 770 reviews
More..
topnotcher

Chat Now!

out of 766 reviews
More..
XXXIAO

Chat Now!

out of 680 reviews
More..
All Rights Reserved. Copyright by AceMyHW.com - Copyright Policy