Project #69453 - help!!

Problem 1:

Management wants to design an assembly line that will turn out 360 units per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: 

Task

Time (sec.)

Immediate Predecessor

A

30

-

B

20

A

C

35

A

D

30

B

E

45

B

F

55

C,D

G

35

D,E

H

20

F,G

      a. Determine the minimum, maximum, and calculated cycle time.

b. What is the minimum number of stations needed?

c. Draw the precedence diagram.

d.  Assign tasks to stations using this rule: assign tasks according to greatest number of following tasks. In case of a tie, use the tiebreaker of assigning task with the longest processing time first. (6 pts)

e. Calculate the efficiency of the system.

 

 

Problem 2:

Following data is given:

          Weekly demand (d) = 140 units/week
          Ordering costs (S) = $20/order

          Holding costs (H) = $1/unit/year 
          Lead time = 6 weeks
          Number of weeks per year = 52 weeks


Suppose the firm uses the EOQ to control the inventory, answer following questions:
a. Determine EOQ? (round it to the nearest integer number) 
b. Find the length of an order cycle (in weeks)? (round it to the nearest integer number) 
c. If you use EOQ as order quantity, what would be the total costs?

d. Find the reorder point (ROP)

   

,G

Subject Mathematics
Due By (Pacific Time) 05/01/2015 12:00 am
Report DMCA
TutorRating
pallavi

Chat Now!

out of 1971 reviews
More..
amosmm

Chat Now!

out of 766 reviews
More..
PhyzKyd

Chat Now!

out of 1164 reviews
More..
rajdeep77

Chat Now!

out of 721 reviews
More..
sctys

Chat Now!

out of 1600 reviews
More..
sharadgreen

Chat Now!

out of 770 reviews
More..
topnotcher

Chat Now!

out of 766 reviews
More..
XXXIAO

Chat Now!

out of 680 reviews
More..
All Rights Reserved. Copyright by AceMyHW.com - Copyright Policy