Project #74883 - question 1

1. Last month a firm made 100 model A's using all of their available labor. If they have already taken orders for 150 model A's for next month, then their planning value must be 1.5. (Points : 1)
        
        

 

Question 2.2. Detailed planning and control is riskier than strategic planning. (Points : 1)
        
        

 

Question 3.3. Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1?

 

1

2

3

4

5

Gross Requirements

 

 

400

500

300

Scheduled receipts

0

0

0

0

0

Projected ending

Inventory

100

100

 

 

 

Net 

Requirements

 

 

 

 

 

Planned

Receipts

 

 

300

 

 

Planned 

Orders

 

 

 

 

 

(Points : 1)
       
       
       
       

 

Question 4.4. Planning numbers are somewhat aggregated (month by month) in: (Points : 1)
       
       
       
       

 

Question 5.5. There is no beginning inventory. What are the net requirements in week 4 if there is a scheduled receipt of 100 units each week and a two week production lead time?

 

1

2

3

4

5

Gross Requirements

500

450

400

500

300

Scheduled receipts

100

100

100

100

100

Projected ending

Inventory

 

 

 

 

 

Net 

Requirements

 

 

 

 

 

Planned

Receipts

450

400

300

300

 

Planned 

Orders

300

300

 

 

 

(Points : 1)
       
       
       
       

 

Question 6.6. Cycle stock can occur at more than one point in a supply chain. (Points : 1)
        
        

 

Question 7.7. Since the booked orders figure represents actual customer demand in a master schedule, that value is always less than or equal to forecasted demand. (Points : 1)
        
        

 

Question 8.8. Which step comes first in sales and operations planning? (Points : 1)
       
       
       
       

 

Question 9.9. Which of these conditions is NOT necessary for the economic order quantity model to be valid? (Points : 1)
       
       
       
       

 

Question 10.10. Within the context of the planning cycle, the planning that takes place at the highest levels of the firm is called: (Points : 1)
       
       
       
       

 

Subject General
Due By (Pacific Time) 06/25/2015 01:00 pm
Report DMCA
TutorRating
pallavi

Chat Now!

out of 1971 reviews
More..
amosmm

Chat Now!

out of 766 reviews
More..
PhyzKyd

Chat Now!

out of 1164 reviews
More..
rajdeep77

Chat Now!

out of 721 reviews
More..
sctys

Chat Now!

out of 1600 reviews
More..
sharadgreen

Chat Now!

out of 770 reviews
More..
topnotcher

Chat Now!

out of 766 reviews
More..
XXXIAO

Chat Now!

out of 680 reviews
More..
All Rights Reserved. Copyright by AceMyHW.com - Copyright Policy