Project #8347 - engineering mathematics

Hi there the question is below

It is a well?]established fact that the labour rate for fixing reinforcing bars depends on  the diameter of bar being fixed: the smaller the bar, the more labour hours per  tonne. The labour hours are also related to the complexity of the work. 
The problem here is, as in most cases, a steel fixer will fix different diameters of bar  at  the  same  time.  However,  it  is  relatively  easy  if  proper  records  are  kept,  to  measure the total hours against the tonnage fixed. 

So,  to  determine  this,  assume  you  have  looked  at  some  previous  records  (past  production figures and timesheets), as given below and use these to determine an  accurate figure in labour hours per tonne for fixing (a) 10mm, and (b) 16mm and (c)  20mm reinforcing bars.: 

Month 1  15 tonnes of 20mm diameter, 12.0 tonnes of 16mm diameter and 8.0 tonnes of  10mm diameter fixed in a total of 539 labour hours. 

Month 2  5 tonnes of 20mm diameter, 9.7 tonnes of 16mm diameter and 6.9 tonnes of 10mm  diameter fixed in a total of 375 labour hours. 

Subject Mathematics
Due By (Pacific Time) 06/29/2013 12:00 am
Report DMCA
TutorRating
pallavi

Chat Now!

out of 1971 reviews
More..
amosmm

Chat Now!

out of 766 reviews
More..
PhyzKyd

Chat Now!

out of 1164 reviews
More..
rajdeep77

Chat Now!

out of 721 reviews
More..
sctys

Chat Now!

out of 1600 reviews
More..
sharadgreen

Chat Now!

out of 770 reviews
More..
topnotcher

Chat Now!

out of 766 reviews
More..
XXXIAO

Chat Now!

out of 680 reviews
More..
All Rights Reserved. Copyright by AceMyHW.com - Copyright Policy